10 Easy Steps to Apply for Rooftop Solar Subsidy Scheme?

An increasing demand of electricity day on day, people are planning to install rooftop solar in their homes to save electricity bill, but at this stage, the cost of solar system installation is slightly on the higher side that’s why they are showing interest, but waiting for government financial support.  MNRE starts providing subsidy on rooftop solar panel installation for residential consumers. But, the main problem was how to apply subsidy for solar? Recently, MNRE introduces National Portal for Rooftop Solar where a consumer can apply rooftop solar themselves. In this blog, you will get to know benchmark cost of rooftop solar, how to apply for subsidy, components, quality and maintenance. Let’s continue reading…

How much cost of rooftop solar through subsidy scheme?

The CFA/subsidy will be available only for applications registered till 31.12.2022 in the National Portal and will be released after clearance by inspecting authority (DISCOM) on successful commissioning and installation of metering system as per specified procedure. The CFA/subsidy will not be applicable with retrospective effect. 

Calculation of CFA/subsidy: The CFA/subsidy would be calculated on the basis of total solar module capacity/solar inverter capacity/capacity approved by DISCOM, whichever is lower.

Illustration for calculation of central Government subsidy

Capacity System Cost Central Subsidy Net Price
3kW ₹1,80,000
₹54,000
₹1,26,000
5kW ₹2,90,000
₹72,000
₹2,18,000
6kW ₹3,48,000
₹81,000
₹2,67,000
8kW ₹4,40,000
₹80,234
₹3,60,000
9kW ₹4,95,000
₹99,000
₹3,96,000
10kW ₹5,50,000
₹1,17,000
₹4,33,000
  

What are the major components and their standard / specifications of rooftop solar?

The below bill of material represents the package of rooftop solar to be offered to the consumer. For relevant specifications, refer to help document section. 

Si. No. Materials Standard / Specification
1 Solar Panel
As per MNRE specification/standards and registered in ALMM
2 On Grid Solar Inverter
As per MNRE/BIS Standard regulations
3
Module Mounting Structure (MMS)
Galvanized as per applicable IS
4
Structure Accessories
Stainless Stell 304
5
Net Meter and Solar meter
As per DISCOM requirements
6
Array Junction Box
Projection as per Inverter requirement
7
AC Distribution Board
Protection as per Inverter & DISCOM/Grid requirement
8
Solar DC Cables & AC Cables
Total 50 metre in length and as per MNRE specifications
9
Earthing
As per MNRE specifications
10 Lighting Arrester MNRE specifications
11 Earthing Cable / Strip MNRE specifications
12
Connectors, Conduit pipes etc
MNRE specifications
13 Accessories
As per requierement
14 Other items required to complete project
As per requierement
15 Installation Testing and Commissioning
As per safety norms of SERC and CEA
16 Civil materials As per MNRE specifications
17 Civil Work As per MNRE specifications
18 Performance Testing Minimum 75%
19 O&M and Warranty 5 Years from the date of commissioning 
 

How to Apply for Rooftop Solar Installation on National Rooftop Portal in 10 Easy Steps?

National Portal for Rooftop Solar

The entire process has been explained in the following steps.

Step-1: Download SANDES app and register on the National Portal by selecting the local Distribution Company or Electricity department, as the case may be, referred as DISCOM, and enter Electricity connection number / Consumer number (mentioned in electricity bill), email id and mobile number. The registration process involves OTP authentication of mobile number and activation through email id. While sending activation link on email, the entire procedure will also be communicated to the applicant.

Step-2: After successful registration the applicant can proceed for submitting application for installation of grid connected rooftop solar system at residential house. The information already entered at the time of registration will be prefilled in the application form and the applicant will have to enter details such as, name on electricity bill, address, capacity of proposed rooftop solar system and details of existing rooftop solar system capacity installed, if any. The applicant also has to upload copy of latest electricity bill. On submission of application, the applicant will get a copy of application on email and it can also be downloaded after login to the portal.

Step-3: Application will be forwarded to the DISCOM for technical feasibility approval as per prevailing regulations. The applicant is advised to initiate installation of the rooftop solar system only after getting the feasibility approval from DISCOM. The technical feasibility approval or rejection, as the case may be, will be informed to the applicant through email.

Step-4: On receipt of feasibility approval from DISCOM, the applicant can proceed to install rooftop solar system. It is mandatory to get the rooftop solar system installed from any of the vendor registered/empanelled with DISCOM. Ministry has specified minimum technical specifications and standards for rooftops solar systems, which are to be followed. The applicant will have the option to choose equipment of higher quality/efficiency. The domestically manufactured solar modules using domestically manufactured solar cells listed in the ALMM should only be used by the applicant. In addition, the inverter should also be BIS certified. In order to protect the interest of the applicant an agreement to be signed between applicant and the vendor and a model format of the agreement is available on National Portal under Help Document section. It is mandatory for the vendor to provide comprehensive maintenance of the rooftop solar plant installed by the firm for at least 5 years.

Step-5: On completion of installation of rooftop solar system, the applicant has to submit project completion details for net-metering and approval (The project completion details will include wattage, make and numbers of solar modules, make and wattage of inverter, name of vendor that has installed the system, uploading of photograph of system, etc). Applicant also has to apply for net-metering. The net-metering application will forwarded to DISCOM and applicant has to follow instructions of DISCOM regarding payment of net-metering charges, signing of net-metering agreement, etc., as applicable.

Step-6: DISCOM officials will install the net-meter and inspect the system for fulfilment of minimum technical specifications and standards.

Step-7: Upon successful inspection and installation of net-meter, commissioning certificate would be generated online by DISCOM.

Step-8: Applicant has to submit bank details and upload copy of cancelled cheque. The fund handling agency will release the central Government subsidy directly into the bank account. The details of central Government subsidy available under simplified procedure may be checked on the National Portal.

sucessful application

Note: The applicant shall also check various informative material placed at Help Document section of the portal for better understanding of the procedure.

Apply fro Rooftop Solar Installation here

Operation and Maintenance Guidelines of Grid Connected PV Plants

1. For the optimal operation of a PV plant, maintenance must be carried out on a regular basis.

2. All the components should be kept clean. It should be ensured that all the components are fastened well at their due place.

3. During mandatory O&M period of 5 years, the rooftop solar PV plant has to be maintained by the vendor for the activity assigned to electrician/technician. The user shall be suitably guided by the vendor for all tasks lying in scope of the user and the user shall also be provided with appropriate documents for such guidance. Maintenance guidelines for various components viz. solar panels, inverter, wiring etc. are discussed below:

1. SOLAR PANELS

Although the cleaning frequency for the panels will vary from site to site depending on soiling, it is recommended that

i. The panels are cleaned at least once every fifteen days.

ii. Any bird droppings or spots should be cleaned immediately.

iii. Use water and a soft sponge or cloth for cleaning.

iv. Do not use detergent or any abrasive material for panel cleaning.

v. Iso-propyl alcohol may be used to remove oil or grease stains.

vi. Do not spray water on the panel if the panel glass is cracked or the back side is perforated.

vii. Wipe water from module as soon as possible.

viii. Use proper safety belts while cleaning modules at inclined roofs etc.

ix. The modules should not be cleaned when they are excessively hot. Early morning is particularly good time for module cleaning.

x. Check if there are any shade problems due to vegetation or new building. If there are, make arrangements for removing the vegetation or moving the panels to a shade-free place.

xi. Ensure that the module terminal connections are not exposed while cleaning; this poses a risk of electric shock.

xii. Never use panels for any unintended use, e. g. drying clothes, chips etc.

xiii. Ensure that monkeys or other animals do not damage the panels.

2. INVERTER

i. The inverter should be installed in a clean, dry, and ventilated area which is separated from, and not directly above, the battery bank (if applicable).

ii. Remove any excess dust in heat sinks and ventilations. This should only be done with a dry cloth or brush.

iii. Check that vermin have not infested the inverter. Typical signs of this include iv. Spider webs on ventilation grills or wasps’ nests in heat sinks. v. Check functionality, e.g. automatic disconnection upon loss of grid power supply, at least once a month.

vi. Verify the state of DC/AC surge arrestors, cable connections, and circuit breakers.

3. CABLES AND CONNECTION BOXES

i. Check the connections for corrosion and tightness.

ii. Check the connection box to make sure that the wires are tight, and the water seals are not damaged.

iii. There should be no vermin inside the box.

iv. Check the cable insulating sheath for cracks, breaks or burns. If the insulation is damaged, replace the wire

v. If the wire is outside the building, use wire with weather-resistant insulation.

vi. Make sure that the wire is clamped properly and that it should not rub against any sharp edges or corners.

vii. If some wire needs to be changed, make sure it is of proper rating and type.

4. SHUTTING DOWN THE SYSTEM

i. Disconnect system from all power sources in accordance with instructions for all other components used in the system.

ii. Completely cover system modules with an opaque material to prevent electricity from being generated while disconnecting conductors.

iii. To the extent possible, system shutdown will not be done during daytime or peak generation.

Other Useful Resources for Consumers, Installers and Manufacturers

1. How to Apply for Rooftop Solar Installation through Subsidy Scheme Application Process

2. Cost of solar system throgh subsidy scheme_CFA

3. Bill of Material Rooftop Solar

4. Technical Specifications

5. Agreement

6. O&M Guidelines

7. ALMM List

8. ALMM Order Declaration

Source: National Portal of Rooftop Solar

16 comments

emzopowertech

emzopowertech

Emzo powertech Company is always known as a good quality in the solar system. And this is a one-time investment offering incredible benefits. Emzo powertech Solar Rooftop Service Provider in Lucknow and be a part of this green environment, world-class and affordable super easy to install and super effective in reducing electricity bills.

Ashok gaur

Ashok gaur

Yes

Khaleel

Khaleel

8978623427

Vinod Kumar Gupta

Vinod Kumar Gupta

Mujhe 5 kilo wad ka solar chahiye

Shivpujan singh Shivpujan singh

Shivpujan singh Shivpujan singh

Aata chakki ke liye sampark karna chahte hain company email id per mera number send Karen Kitna kharch aata hai

Dinesh Sharma

Dinesh Sharma

Hii

Santosh Kumar maurya

Santosh Kumar maurya

Call

Sonveer sharma

Sonveer sharma

Pls contact me

miecmiys

miecmiys

10 Easy Steps to Apply for Rooftop Solar Subsidy Scheme?
[url=http://www.gq6usezd315921nipv710l3q66p56u0ss.org/]umiecmiys[/url]
miecmiys http://www.gq6usezd315921nipv710l3q66p56u0ss.org/
amiecmiys

betsiilpmn

betsiilpmn

10 Easy Steps to Apply for Rooftop Solar Subsidy Scheme?
abetsiilpmn
[url=http://www.g443q65wn6iiw17g711m93g9n83qpoyjs.org/]ubetsiilpmn[/url]
betsiilpmn http://www.g443q65wn6iiw17g711m93g9n83qpoyjs.org/

sqxjbwxmsi

sqxjbwxmsi

10 Easy Steps to Apply for Rooftop Solar Subsidy Scheme?
asqxjbwxmsi
[url=http://www.gnta246im918wyz8eoh5p624i52x74h1s.org/]usqxjbwxmsi[/url]
sqxjbwxmsi http://www.gnta246im918wyz8eoh5p624i52x74h1s.org/

Dixieanolo

Dixieanolo

Bro – 10 Easy Steps to Apply for Rooftop Solar Subsidy Scheme? – Best info!
-

Лучший сайт для покупки и продажи товаров – Кракен https://xn—krkn-6q5a9f.com . Сегодня Kraken даркнет является самой крупной и известной торговой анонимной площадкой в РФ. Она предлагает свои пользователям доступ к большой базе магазинов из разных стран. Здесь можно приобрести любые товары. Также вы можете сами начать продажу, зарегистрировавшись на проекте. При этом важно понимать, что сайт гарантирует безопасность, а потому проверяет каждого своего продавца. Для этого используются различные способы, в числе которых – тайные покупатели. Потому вы можете быть уверены в качестве покупаемых товаров, честности продавцов, и безопасности покупок на Kraken онион. А для перехода на сайт, просто использовать активную ссылку Kraken официальный сайт – https://xn—2rn-7ua.cc.

Re: [url=https://xn—2ran-g0a.com]kraken [/url]

jrehfure9o1

[url=https://aljarmaq.net/post/18058/%D9%86%D8%AA%D9%86%D9%8A%D8%A7%D9%87%D9%88-%D9%8A%D9%88%D8%B5%D9%8A-%D9%88%D8%B2%D8%B1%D8%A7%D8%A1-%D8%AD%D9%83%D9%88%D9%85%D8%AA%D9%87-%D8%A8%D8%B9%D8%AF%D9%85-%D8%A7%D9%84%D8%AA%D8%AD%D8%AF%D8%AB-%D8%B9%D9%86-%D8%A8%D8%A7%D9%8A%D8%AF%D9%86]кракен[/url]
[url=https://de.oneill.com/blogs/all/gore-tex-alles-was-du-wissen-solltest?comment=136070398280#comments]ссылка на кракен[/url]
[url=https://aljarmaq.net/public/post/7492/%D8%A7%D9%84%D8%B3%D8%A7%D8%AF%D8%B3-%D9%85%D9%86-%D8%B9%D8%A7%D8%A6%D9%84%D8%AA%D9%87-%D9%85%D9%82%D8%AA%D9%84-%D8%B4%D8%A7%D8%A8-%D9%81%D9%8A-%D8%A7%D9%84%D8%B9%D8%B4%D8%B1%D9%8A%D9%86%D9%8A%D8%A7%D8%AA-%D9%85%D9%86-%D8%B9%D9%85%D8%B1%D9%87-%D9%81%D9%8A-%D8%A3%D9%85-%D8%A7%D9%84%D9%81%D8%AD%D9%85]ссылка на кракен[/url]
[url=https://aljarmaq.net/post/15651/%D8%AF%D8%B9%D9%88%D8%A7%D8%AA-%D9%84%D8%AA%D8%B8%D8%A7%D9%87%D8%B1%D8%A9-%D8%B6%D8%AF-%D8%A5%D8%B2%D8%A7%D9%84%D8%A9-%D8%A7%D9%84%D9%86%D8%B5%D8%A8-%D8%A7%D9%84%D8%AA%D8%B0%D9%83%D8%A7%D8%B1%D9%8A-%D9%84%D9%84%D8%B4%D9%87%D8%AF%D8%A7%D8%A1-%D9%81%D9%8A-%D8%A7%D9%84%D9%84%D8%AC%D9%88%D9%86-%D8%A7%D9%84%D9%85%D9%87%D8%AC%D8%B1%D8%A9]кракен ссылка тор[/url]
[url=https://www.wilkinswalk.com/blogs/blogger/nike-air-vapormax?comment=130203058340#comments]кракен онион[/url]
[url=http://remgen.ru/blog/starter-denso-128000-1150-128000-1151-128000-1152-228000-3610-john-deere-am100807-am100809-ty25236-yanmar-119305-77010-119620-77011#comment_808112]kraken[/url]
[url=https://onetierra.mx/blog/azuga-es-el-numero-1-en-la-clasificacion-de-g2-de-software-de-gestion-de-flotas/#comment-298137]кракен ссылка vk2 top[/url]
[url=https://de-creativeescaperooms.glopalstore.com/blogs/how-to-articles/how-to-use-a-caesar-cipher-wheel?comment=133890834724#comments]kraken darknet[/url]
[url=https://satsis.info/forum/post/773953.html#773953]kraken darknet[/url]
[url=https://aljarmaq.net/post/14985/%D8%A8%D8%A7%D9%84%D9%81%D9%8A%D8%AF%D9%8A%D9%88-%D8%A7%D9%84%D8%B9%D8%B4%D8%B1%D8%A7%D8%AA-%D9%8A%D8%B4%D8%A7%D8%B1%D9%83%D9%88%D9%86-%D9%81%D9%8A-%D8%AC%D9%86%D8%A7%D8%B2%D8%A9-%D8%B1%D9%85%D8%B2%D9%8A%D8%A9-%D9%84%D9%84%D8%B4%D9%87%D9%8A%D8%AF%D8%A9-%D8%A7%D9%84%D8%A3%D8%B3%D9%8A%D8%B1%D8%A9-%D8%B3%D8%B9%D8%AF%D9%8A%D8%A9-%D9%85%D8%B7%D8%B1]kraken ссылка[/url]
07c6bcb

AsiansMeexy

AsiansMeexy

Hello guys! Nice article 10 Easy Steps to Apply for Rooftop Solar Subsidy Scheme?
Новый даркнет мега маркет площадка, достойная замена hydra в даркнете. Мгновенные переводы – после оплаты позиции деньги сиюминутно зачисляется на счет продавца. Шифрование данных – личные данные о покупателе надежно защищены от посторонних. Мега СБ мега зеркало – это достойная площадка с большим ассортиментом товара и чесными дилерами.

[url=https://xn—mgasb-6za.com]мега сб[/url]

mega-sb
не могу зайти на мегу
мега дарк
адрес меги
мега сб

ph99bGGoma

Sanjay Kumar modi

Sanjay Kumar modi

Ongird

Ashish

Ashish

Contect no sir ji

Goldy Yadav

Goldy Yadav

Call me

Leave a comment

সর্বাধিক বিক্রিত পণ্য

Engineer VisitEngineer Visit
Loom Solar Engineer Visit
Sale priceRs. 1,000 Regular priceRs. 2,000
Reviews
Dealer RegistrationLoom Solar Dealer Registration
Loom Solar Dealer Registration
Sale priceRs. 1,000 Regular priceRs. 5,000
Reviews

জনপ্রিয় পোস্ট

  1. Buying a Solar Panel?
  2. Top 10 Solar Companies in India, 2024
  3. This festive season, Power Your Home with Solar Solutions in Just Rs. 7000/- EMI!
  4. Top Lithium Battery Manufacturers in World, 2024
  5. How to Install Rooftop Solar Panel on Loan?